Gray Quantity Surveyors

Applying for an Extension of Time: Why Documentation and Professional Oversight Matter

Delays in construction projects are often unavoidable. Among the most common causes are adverse weather conditions, unforeseen ground conditions, or design changes. When a delay occurs, contractors may be entitled to an Extension of Time (EOT) under the terms of their contract. However, applying for an EOT is not as simple as notifying the employer or project manager; it requires a structured approach, robust evidence, and professional oversight.

Understanding Extension of Time

An Extension of Time is a contractual mechanism that allows contractors to extend the completion date of a project without being penalised for liquidated damages. Contracts such as the JCT (Joint Contracts Tribunal) or NEC (New Engineering Contract) recognise EOTs for delays caused by events outside the contractor’s control. These can include exceptionally adverse weather, employer-caused delays, or other “Relevant Events” as defined in the contract.
However, entitlement to an EOT is never automatic. The contractor must demonstrate that the delay was caused by a qualifying event and provide sufficient evidence to substantiate the claim. Without proper documentation, the claim is often weak, leading to disputes or outright rejection.

The Importance of Records

Documentation is the backbone of any successful EOT claim. Without detailed records, a contractor’s entitlement can be difficult to prove. Essential records include:
  • Daily Site Logs: Record work completed, labour hours, materials delivered, and weather conditions.
  • Photographic Evidence: Images showing site conditions, damage, or disruption.
  • Programme Updates: Regularly updated project schedules showing the impact of delays on critical paths.
  • Correspondence: Emails, letters, and meeting minutes related to delays and mitigation measures.
These records create a clear trail that links the delay to the qualifying event. In other words, they provide the evidence that demonstrates a direct cause-and-effect relationship between the event and the impact on the project programme.

Establishing a Clear Link: Event to Delay

A common reason EOT claims fail is the lack of a clear connection between the disruptive event and the delay to project completion. Contractors must clearly show that:
  1. The Event Occurred: Provide evidence that the weather event or other delay-causing factor actually took place. For example, a contractor can reference meteorological reports for adverse weather or delivery logs for material delays.
  2. The Event Caused Delay: Demonstrate how the event directly impacted critical elements of the project programme. Simply stating that rain occurred is insufficient; the contractor must show how work on the critical path was affected.
  3. Delay Was Beyond Contractor Control: Contractors are responsible for managing ordinary risks, such as typical seasonal weather. Only events outside normal expectations generally justify an EOT.
A well-prepared EOT claim will use the project programme to illustrate exactly how the delay altered the completion date. Gantt charts, critical path analysis, and updated schedules are invaluable tools in showing this link.

The Role of a Quantity Surveyor

Involving a professional quantity surveyor (QS) in the EOT process can make a significant difference. A QS brings expertise in both contractual interpretation and evidence management, ensuring that claims are both fair and well-documented.
How a QS Helps
  1. Assessment of Delay: A QS can review the programme, identify critical path impacts, and quantify the effect of delays on the overall project completion.
  2. Evidence Compilation: QSs know exactly what records are required to support an EOT claim, from weather logs to correspondence and site diaries.
  3. Fair and Objective Reporting: A QS provides impartial analysis, increasing credibility with the employer or project manager. Their reports clearly demonstrate the link between the delay-causing event and the programme impact.
  4. Dispute Avoidance: With accurate records and professional oversight, EOT claims are less likely to escalate into disputes. Even if disagreements arise, a QS-prepared claim stands up well under review.
By integrating a QS into the process early, contractors ensure their claim is not only compliant with contract requirements but also presents a compelling, evidence-backed case.

Steps to Prepare an EOT Claim

  1. Immediate Record-Keeping: From the moment a delay occurs, start documenting all relevant information. Include weather conditions, labour productivity, material availability, and any mitigation measures.
  2. Programme Updates: Maintain a current project programme, highlighting critical path tasks and showing the impact of delays.
  3. Notification: Follow the contractual requirements for notifying the employer or project manager of the delay. Timing is often critical; late notifications can jeopardise entitlement.
  4. Evidence Compilation: Collect logs, correspondence, photographs, and any other supporting documentation.
  5. Professional Assessment: Engage a QS to review the evidence, quantify the delay, and prepare a structured claim that clearly demonstrates entitlement.
  6. Submission: Present the claim formally, including all evidence and programme updates, ensuring it meets the contract’s procedural requirements.

Common Pitfalls

Even with strong evidence, EOT claims can fail due to common mistakes:
  • Late Notification: Contracts often specify strict timelines for notifying delays. Missing deadlines can result in claims being invalid.
  • Inadequate Records: Without daily logs, weather reports, and programme updates, proving the link between the event and the delay is difficult.
  • Failure to Update Programme: Outdated or incomplete programmes make it hard to show critical path impacts.
  • Lack of Professional Oversight: Contractors attempting to handle claims without expert input risk incomplete or inconsistent documentation.
Avoiding these pitfalls is crucial to protecting contractual rights and minimising disputes.

Conclusion

Applying for an Extension of Time is not a simple procedural step—it is a structured process that requires careful planning, diligent record-keeping, and professional oversight. Contractors must demonstrate a clear connection between the delay-causing event and its impact on the project programme. Involving a quantity surveyor ensures that claims are accurately assessed, evidence is correctly submitted, and entitlement is fairly evaluated.
At Gray Quantity Surveyors, we support contractors and employers in navigating EOT claims effectively. From maintaining accurate records to preparing professional submissions, our team ensures that claims are robust, compliant, and credible. Properly managed, an EOT claim safeguards both time and financial interests, keeping projects on track and avoiding unnecessary disputes.
Whether you are facing adverse weather, design changes, or unforeseen site conditions, a structured approach to EOT claims protects your project and strengthens your contractual position.
Scroll to Top